We are planning to invest £33.3M to boost the electricity network in the local area.

We are preparing to submit a planning application to allow us to install approximately 4.6km of new electricity cables, and connect them to a new electricity substation, which would be built as part of the project. The cables would be laid underground.

The proposed new substation would be accessed off Blanket Street in West Worldham. Download our design of the substation, to see what is proposed. 

The project would provide visual improvement to the local landscape

If approved, the scheme would see 7,281 meters of overhead line removed from view around Worldham. Download our map at the bottom of this page to see where the overhead lines would be removed.

Removing this section of overhead lines would also reduce the number of access requests made to landowners, for future maintenance works.

The planning application is scheduled to be submitted shortly. If granted, it would allow the unground cables to be connected, from new and existing overhead power lines to a new electricity substation along three separate routes. Read our FAQs below for details on the cable routes.

Once submitted, a decision on the planning application is expected within six months (but is subject to change). In the meantime, we remain in conversation with landowners with regards to obtaining voluntary agreement for land rights. A Compulsory Purchase Order would only be used as a last resort to acquire the land and land rights necessary for the project.

If the application is approved, work on the project could start as early as November 2024 and take up to 24 months to complete. There are no planned power cuts scheduled to take place should the project get the go-ahead. All dates are subject to change.

Community events

The team is also exploring the possibility of hosting community events in the coming months, which will be advertised ahead of time on this page. 

Why are these works being proposed?

As a result of significant developments in and around the Alton area, the existing electricity network is unable to meet the forecast increase in demand over the coming years. In addition, the project would bolster the power supply in Fernhurst, providing the town with an energy buffer, in case of an outage. To overcome this shortfall in capacity, we propose installing a new primary substation in West Worldham.

The new substation could also allow for future low carbon technologies to be connected to the electricity grid. This investment will ensure the electricity network is resilient for years to come, keeping essential power flowing to those living and working in the area.

What is a Compulsory Purchase Order?

A Compulsory Purchase Order (CPO) is a legal mechanism by which land and land rights can be acquired, without the consent of the owner, where it is in the public interest or for the greater public good. A CPO can be used for infrastructure projects such as new roads, new railways, new housing, and both electricity cables and substations.

For more information on land rights and new connections, read our FAQs below or visit our Land Rights page. 

We have the environment in mind

The works are futureproofing and strengthening your area’s power supply to cope with severe weather events. It will also help support greater uptake of low carbon technologies.

Discover more on our Smarter Electricity page.

Get in touch 

We want to be a good neighbour to you and help answer any questions you may have.

Have a query?

Have a complaint?

Need extra support during a power cut?

Commonly asked questions

Download our documents