What is Connections Reform?

Connections Reform is a major overhaul of the electricity transmission connections process led by the National Energy System Operator (NESO).

This new initiative aims to speed up connections for vital net zero projects and removes unviable developments from the connections queue. On the 15 April 2025, Ofgem approved the proposed Connections Reforms by NESO which will transform the connections process to better facilitate clean power for 2030 and beyond.

The main objective of Connections Reform is to create a connections queue, aligned with the CP30 Action Plan, with three key features:

  • Viability – by prioritising ‘ready’ projects, the Gate 2 queue is made up of projects that are demonstrably viable and progressed (having land rights or sufficiently progressed their planning status).

  • Need – by aligning with the CP2030 Action Plan, and any future strategic alignment criteria set by the Government, the Gate 2 queue is made up of projects that best meet current and future system need.

  • Efficiency – the mix of ready projects aligned with Strategic Alignment Criteria is preserved, with projects that drop out being replaced by projects with the same technology.

This will enable an increased rate of connections through efficient network build and increase customer confidence in connections to enable investment. Once implemented, this will result in a more efficient process and network design, benefitting both customers and consumers.  


Connections Reform Update​

We’re pleased to be able to share some valuable insights on how the connections reform process is moving forward, and what we’ve seen so far from some of your Gate 2 submissions. 

We’ve now tallied Already Connected, Protected and Ready projects in our central southern England licence area from our recent submissions to NESO. These are all compared against the Clean Power 2030 and 2035 targets for each technology. 

This isn’t yet a complete picture - for instance, it doesn’t include large customers who must apply to the NESO - but it still gives a sense of likely trends. We've focused on our central southern England region for now, as most customers in our Scottish network area applied directly to NESO, as they’re above the 10MW threshold for large, embedded generation projects in Scotland. We’ve yet to get full visibility of these applications fromNESO; but once we get it, we’ll provide this data for you.

We would like to say thank you to all our customers for their commitment and effort in submitting Gate 2 applications. This is a major stepforward in the wider connections reform process, helping streamline access to the grid and accelerate the transition to a cleaner, even moreefficient electricity system. 

A reminder - these projects are now under review by NESO for strategic alignment with its stated goals before a new connections queue is alignedwith Clean Power capacity quotas.

In total, we submitted:​

231 projects (totalling 8,261.2 MW) in our central southern England region. 

57 projects (totalling 234 MW) in our north of Scotland region. 

We'll share further updates as NESO progresses with its review. In the meantime, if you’ve any questions, please get in touch with us at reformsupport@sse.com.

 

Latest Developments

  • Connections Reform Timeline Update for 2025 & 2026​

    On 2 October, NESO published an updated timeline to deliver Connections Reform across 2025 and 2026. All Gate 1 offers are to be issued by the end of Q1 2026. Gate 2 offers for customers connecting upto 2030 are to be issued by the end of Q2 2026, with Gate 2 offers for customers connecting after 2030 to be issued by Q3 2026. The submission window for new applications is expected to open in Q1 2026.

  • Government's Clean Power 2030 (CP30) Action Plan

    The UK government have set out an action plan for reaching their target of clean power by 2030 to increase energy security and improve affordability, while reducing greenhouse gas emissions. To meet these targets, NESO have published capacity ranges for solar, onshore wind and batteries to 2030 and 2035 across DNO licence areas to help achieve clean power.

  • Implementing Connections Reform (CMP434)

    CUSC Modification Proposal 434 (CMP434) introduces a gated application process for newapplications with two formal stages – Gate 1(indicative offer) and Gate 2 (confirmed offer). Toprogress to Gate 2 and receive a connection offer,customers must meet 'Readiness' and 'Alignment'criteria. The first CMP434 application window is toopen in 2026 for new applications.

Relevant Links

SSEN Submission Portal

To support customers through the Gate 2 process, SSEN launched a dedicated evidence portal, enabling users to securely submit their Gate 2 documentation. The portal was open from 19 May to 26 August for customers with existing connection agreements. During this period, we received a total of 288 submissions across our two licence areas.


Looking ahead, customers seeking new connection applications will also need to meet the Gate 2 readiness criteria. The first application window to NESO for new customers is expected to open in early 2026.

If any new customers or customers with a Gate 1 offer wish to apply for a Gate 2 offer, please email us at reformsupport@sse.com to inform us and we can set you up on our Gate 2 submission portal. 

The evidence customers will need to submit is briefly summarised here, Connections Reform – What’s next for SSEN Distribution customers – SSEN, with the detail found within NESO’s Gate 2 Criteria Methodology.

SSEN Connections Reform Webinar recap


Webinar and Contact

SSEN regularly holds informative webinars for our customers and stakeholders, including a mini-series on Connections Reform topics. Keep up to date with the latest and upcoming webinars here - Home | SSEN

For further information and support, please reach out to our team at connections@ssen.co.uk

Contact us

External Links / Updates