As the Distribution Network Operator for the north of Scotland, we own and operate the 33 kilovolt (kV) and 11kV networks on Shetland, which are made up of approximately 1,650 km of overhead lines and underground cables operating at distribution voltages (33kV and below).

Our network

Sub Sea cable
There are no overhead lines or underground cables operating at transmission voltages (132kV and above) on Shetland.

During the introduction of the British Electricity Trading and Transmission Arrangements (BETTA) of 2005, it was formally agreed that we would also administer electricity generation as well as network operation on Shetland, although we had been fulfilling this role for some time before this.  

This means that, as we are responsible for balancing the islands’ supply and demand, we are also the System Operator (SO) on Shetland.

Existing arrangements

Most of Shetland’s electricity is currently supplied by two fossil-fuel power stations, with the remainder being supplied by renewable generators.  

Shetland’s main electricity generation sources are:  

Lerwick Power Station (LPS)

A 72.8MW diesel-fired station that provides around 50% of Shetland’s electricity on an annual basis.  We’ve recently installed a new engine and 8MW battery to supplement the existing station, and to further increase the amount of renewable generation which can be accommodated on the network. 

The station was built in 1953 and is approaching the end of its scheduled full-duty operational life, however the station is still very much a part of our future plans, which you can read about here and also further down the page in the “Standby Proposals” section.

Sullom Voe Terminal (SVT) Power Station

An independently owned gas-fired power station, which meets around 30% of Shetland’s demand. The station’s primary purpose is to supply electricity to the Sullom Voe gas terminal, but it also provides power to the Shetland system through a contractual arrangement. 

Renewables

A number of small independent and community-based renewable generators, including wind and tidal, which currently contribute around 20% of the islands’ electricity supply. 

Most of these generators are managed by the Shetland Active Network Management (ANM) system, which originated in an innovative trial project developed by SSEN in partnership with third parties called the Northern Isles New Energy Solution (NINES).

The ANM aims to increase renewable generation output and reduce reliance on fossil fuels on the island network, taking advantage of the above-average wind conditions that Shetland experiences. 

Looking to the future 

Gremista Grid Supply Point

Electricity is currently distributed on Shetland via our 33kV distribution network.  

Once the Shetland Islands are connected to mainland GB via the new High Voltage Direct Current (HVDC) subsea cable and the new onshore 132kV network currently under construction by SSEN Transmission, the distribution and transmission networks will need to be connected at a new substation – this is what is known as a Grid Supply Point (GSP). 

We are working jointly with SSEN Transmission to develop and construct the new GSP on land close to the existing Lerwick Power Station (LPS).
Construction works

SSEN Distribution appointed island-based Tulloch Developments as its principal contractor to construct the development platform for the GSP – including associated earthworks and drainage.  Works progressed well and the platform was handed over to SSEN Transmission in September 2023 to undertake the civil and electrical works required to construct the GSP with commissioning planned throughout the second half of 2025, civils construction works are now complete.

Keeping the power flowing - standby proposals

Once the islands are connected to the mainland GB electricity system via SSEN Transmission’s 600MW HVDC transmission link this will supply Shetland’s demand needs for the vast majority of the time, however a standby solution is also required to ensure homes and businesses continue to receive the power they need during transmission system outages.

At the time of submitting our RIIO-ED2 business plan there was uncertainty over the costs of these standby supply arrangements.  To provide the most efficient solution for consumers, we required time to complete our procurement process to provide increased certainty on the costs required to implement the solution. In November 2022 Ofgem decided to implement the Shetland Enduring Solution uncertainty mechanism re-opener to provide the time to complete the procurement process.

In January 2024, having reviewed options for a reliable, innovative and cost-effective backup solution to support the security of supply to Shetland, we submitted our justification to Ofgem for approval; whereby SHEPD would procure the required fault ride-through and blackout avoidance equipment as a service, for a 10-year period, while retaining LPS as the standby generation.

As part of the whole system solution for Shetland, our standby solution is required to be available at the same time as our connection to the Transmission network at the GSP in Gremista to ensure the standby solution is available for any planned or unplanned outages on the Transmission network or HVDC link.

To meet these timescales:

  • Tulloch Developments commenced the construction of the civils platform for the standby solution on land adjacent to the GSP in August 2023 with completion on schedule for April 2024. 
  • Our proposed third-party service provider submitted their planning application to the Scottish Government Energy Consents Unit (ECU) in November 2023.

Timely decisions on both the reopener submission and the ECU planning application are of critical importance to delivering the project in 2025 and we will continue to provide all the support and information required to the relevant parties.

View our Shetland Standby Solution Brochure here.

Submissions and regulatory papers

More information

For more details on our standby proposals, please see page 92 of our RIIO-ED2 Business Plan

RIIO-ED2 Business Plan