  • Queue Management

    Queue Management

    After you’ve accepted your quote your connection may be affected by others that are awaiting network reinforcement, before they can connect. This is called the ‘connection queue’.

  • Milestones

    The milestones we apply in our connection queue are:

    • initiated planning permission process
    • secured planning permission
    • secured land consents
    • Initiated Transmission System Operator interface
    • Works begun
    • Complete construction
  • Material change

    Please note that if you request a change to your connection after you have accepted the offer, it may affect your position in the queue. For more information on what changes may impact queue position please see the ENA website.

  • Industry best practice

    These milestones as well as the definition of what constitutes a material change, were consulted on in 2016 and agreed by industry as the best way for DNOs to ensure that connections progressed as efficiently as possible. Read more about the milestones consultation and material change consultation, as well as stakeholder feedback on the ENA website